| ID | Task Name | Duration | Start Date | Finish Date | Predecessors | Resource Names |
|---|
| 0 | TA_04 | 193 wks | 11/01/2001 8:00 | 7/13/2005 17:00 | n/a | n/a |
| 1 | Activity 1: Proj. Mgmt/Prep Work Plan | 70 wks | 6/03/2002 8:00 | 10/03/2003 17:00 | n/a | Halff |
| 2 | Project Charter | 3 wks | 6/24/2002 8:00 | 7/12/2002 17:00 | n/a | Halff |
| 3 | Project Fact Sheet | 4 wks | 6/17/2002 8:00 | 7/12/2002 17:00 | n/a | Halff |
| 4 | Organization Chart | 9.2 wks | 6/03/2002 8:00 | 8/05/2002 17:00 | n/a | Halff |
| 5 | Schedule | 9 wks | 6/03/2002 8:00 | 8/02/2002 17:00 | n/a | Halff |
| 6 | Project Expenditure Curve | 70 wks | 6/03/2002 8:00 | 10/03/2003 17:00 | n/a | Halff |
| 7 | Project Contact List | 8.6 wks | 6/03/2002 8:00 | 7/31/2002 17:00 | n/a | Halff |
| 8 | Activity 2: Select Engineering/Mapping Team | 20.4 wks | 11/01/2001 8:00 | 3/22/2002 17:00 | n/a | LCRA |
| 9 | Prep SOQ | 4.6 wks | 11/01/2001 8:00 | 12/03/2001 17:00 | n/a | n/a |
| 10 | Issue SOQ | 0 mo | 12/07/2001 8:00 | 12/07/2001 8:00 | 9 | n/a |
| 11 | SOQ Prep by Vendors | 4.2 wks | 12/07/2001 8:00 | 1/04/2002 17:00 | 10 | n/a |
| 12 | SOQ due to LCRA | 0 days | 1/04/2002 17:00 | 1/04/2002 17:00 | 11 | n/a |
| 13 | Review and Select Vendor | 1 wk | 1/07/2002 8:00 | 1/11/2002 17:00 | 12 | n/a |
| 14 | Rec Memo to Contracting | 0 mo | 1/11/2002 17:00 | 1/11/2002 17:00 | 13 | n/a |
| 15 | Prep Notice of Selection | 3 days | 1/14/2002 8:00 | 1/16/2002 17:00 | 14 | n/a |
| 16 | Issue Notice of Selection | 0 mo | 1/18/2002 8:00 | 1/18/2002 8:00 | 15 | n/a |
| 17 | Negot. PSA Terms & TO 1 $ | 23 days | 1/18/2002 8:00 | 2/19/2002 17:00 | 16 | n/a |
| 18 | Purch Issue PSA For Vendor Sign | 0 wks | 2/19/2002 17:00 | 2/19/2002 17:00 | 17 | n/a |
| 19 | Vendor Review and Signs and Returns PSA | 1 wk | 2/20/2002 8:00 | 2/26/2002 17:00 | 18 | n/a |
| 20 | Vendor Ships PSA to LCRA Purchase | 0 mo | 2/26/2002 17:00 | 2/26/2002 17:00 | 19 | n/a |
| 21 | Purchasing Ok's Board Agenda Item | 1 wk | 2/27/2002 8:00 | 3/05/2002 17:00 | 20 | n/a |
| 22 | LCRA Board Action for Selection of Mapping Team | 0 days | 3/20/2002 8:00 | 3/20/2002 8:00 | 21 | n/a |
| 23 | Purchase Exec. PSA | 3 days | 3/20/2002 8:00 | 3/22/2002 17:00 | 22 | n/a |
| 24 | Issues P.O. & Task Order 1 NTP | 0 days | 3/22/2002 17:00 | 3/22/2002 17:00 | 23 | n/a |
| 25 | Activity 3: Funding Requests | 6 wks | 8/21/2002 8:00 | 10/01/2002 17:00 | n/a | LCRA |
| 26 | Activity 4: Map Master Plan | 84 wks | 6/03/2002 8:00 | 1/09/2004 17:00 | 22 | Halff |
| 27 | Define jurisdiction | 3 wks | 6/03/2002 8:00 | 6/21/2002 17:00 | n/a | Halff |
| 28 | Assess Area Mapping Needs | 84 wks | 6/03/2002 8:00 | 1/09/2004 17:00 | n/a | Halff |
| 29 | MNUSS Database | 6.2 wks | 6/03/2002 8:00 | 7/15/2002 17:00 | n/a | Halff |
| 30 | Tiling System | 20.2 wks | 7/15/2002 8:00 | 12/02/2002 17:00 | n/a | Halff |
| 31 | Develop map needs index & classify level of need | 26.2 wks | 6/03/2002 8:00 | 12/02/2002 17:00 | n/a | Halff |
| 32 | Map Needs Prioritization Index (Draft) | 25.28 wks | 6/03/2002 8:00 | 12/02/2002 17:00 | n/a | Halff |
| 33 | Map Needs Index Delivered to LCRA | 0 wks | 12/02/2002 17:00 | 12/02/2002 17:00 | 32 | Halff |
| 34 | TCRFC Review of Draft Index | 4.8 wks | 12/03/2002 8:00 | 1/03/2003 17:00 | 33 | TCRFC |
| 35 | Map Needs Prioritization Index (Final) | 24.8 wks | 1/06/2003 8:00 | 6/26/2003 17:00 | 34 | Halff |
| 36 | Map Needs Assessment and Community Ranking | 24.6 wks | 6/27/2003 8:00 | 12/16/2003 17:00 | 35 | Halff |
| 37 | Prioritize production for DFIRM | 6 wks | 10/03/2003 8:00 | 1/09/2004 17:00 | 36 | Halff |
| 38 | Define the Framework for a Map Maintenance Plan | 21.8 wks | 12/03/2002 8:00 | 5/02/2003 17:00 | 32 | Halff |
| 39 | Develop Cost Estimates | 7 wks | 12/02/2002 8:00 | 1/17/2003 17:00 | n/a | Halff |
| 40 | Cost for DFIRM Panel Production | 3.2 wks | 12/02/2002 8:00 | 12/23/2002 17:00 | n/a | Halff |
| 41 | Develop preliminary budgets for map maintenance activities | 3.2 wks | 12/02/2002 8:00 | 12/23/2002 17:00 | n/a | Halff |
| 42 | Coordinate with TNRIS | 4 wks | 12/23/2002 8:00 | 1/17/2003 17:00 | n/a | Halff |
| 43 | Funding Options | 6.8 wks | 1/15/2003 8:00 | 3/03/2003 17:00 | n/a | Halff |
| 44 | Confirm the selected counties (Bastrop & Wharton) | 3 wks | 6/03/2002 8:00 | 6/21/2002 17:00 | n/a | TCRFC |
| 45 | Scheduling & Implementation | 46.8 wks | 6/03/2002 8:00 | 4/24/2003 17:00 | n/a | Halff |
| 46 | Map Master Plan (Draft & Final) | 46.8 wks | 6/03/2002 8:00 | 4/24/2003 17:00 | 22 | Halff |
| 47 | Map Master Plan Outline | 17.2 wks | 6/03/2002 8:00 | 9/30/2002 17:00 | n/a | Halff |
| 48 | Map Master Plan Draft | 28.2 wks | 6/03/2002 8:00 | 12/16/2002 17:00 | n/a | Halff |
| 49 | Delivery of Map Master Plan Draft to LCRA | 0 wks | 12/16/2002 17:00 | 12/16/2002 17:00 | 48 | Halff |
| 50 | Map Master Plan Review of Draft | 2.2 wks | 12/17/2002 8:00 | 12/31/2002 17:00 | 49 | LCRA |
| 51 | Map Master Plan Final | 8.8 wks | 1/01/2003 8:00 | 3/03/2003 17:00 | 50 | Halff |
| 52 | Map Master Plan Final Review | 7.6 wks | 3/04/2003 8:00 | 4/24/2003 17:00 | 51 | LCRA |
| 53 | Map Master Plan Complete | 0 wks | 4/24/2003 17:00 | 4/24/2003 17:00 | 52 | Halff |
| 54 | Activity 5: Development of Floodways | 39.2 wks | 6/10/2002 8:00 | 3/10/2003 17:00 | n/a | Halff |
| 55 | Activity 5: Development of Floodways-Wharton | 39.2 wks | 6/10/2002 8:00 | 3/10/2003 17:00 | n/a | Halff |
| 56 | Development of Basic RAS Model | 15.2 wks | 6/10/2002 8:00 | 9/23/2002 17:00 | n/a | Halff |
| 57 | Development of Multiple Profiles | 1.2 wks | 9/24/2002 8:00 | 10/01/2002 17:00 | 56 | Halff |
| 58 | Floodway Computations | 15 wks | 10/02/2002 8:00 | 2/03/2003 17:00 | 57 | Halff |
| 59 | Plot Floodplains & Floodways | 4.4 wks | 2/04/2003 8:00 | 3/05/2003 17:00 | 58 | Halff |
| 60 | Documentation | 2.2 wks | 2/24/2003 8:00 | 3/10/2003 17:00 | n/a | Halff |
| 61 | Tech Memo on Floodway Computations | 2.2 wks | 2/24/2003 8:00 | 3/10/2003 17:00 | n/a | Halff |
| 62 | Submittal of Preliminary Floodway Computations and Maps to LCRA | 0 wks | 3/10/2003 17:00 | 3/10/2003 17:00 | 61 | Halff |
| 63 | Activity 5: Development of Floodways-Bastrop | 39.2 wks | 6/10/2002 8:00 | 3/10/2003 17:00 | n/a | Halff |
| 64 | Development of Basic RAS Model | 15.2 wks | 6/10/2002 8:00 | 9/23/2002 17:00 | n/a | Halff |
| 65 | Development of Multiple Profiles | 1.2 wks | 9/24/2002 8:00 | 10/01/2002 17:00 | 64 | Halff |
| 66 | Floodway Computations | 17.8 wks | 10/02/2002 8:00 | 2/03/2003 17:00 | n/a | Halff |
| 67 | Plot Floodplains & Floodways | 4.4 wks | 2/04/2003 8:00 | 3/05/2003 17:00 | 66 | Halff |
| 68 | Documentation | 2.2 wks | 2/24/2003 8:00 | 3/10/2003 17:00 | n/a | Halff |
| 69 | Tech Memo on Floodway Computations | 2.2 wks | 2/24/2003 8:00 | 3/10/2003 17:00 | n/a | Halff |
| 70 | Submittal of Preliminary Floodway Computations and Maps to LCRA | 0 wks | 3/10/2003 17:00 | 3/10/2003 17:00 | 69 | Halff |
| 71 | Activity 6: Prep & Submit Tech Support Notebook | 56.8 wks | 7/16/2002 8:00 | 8/15/2003 17:00 | 24 | Halff |
| 72 | Basinwide TSDN | 24 wks | 7/16/2002 8:00 | 12/30/2002 17:00 | n/a | Halff |
| 73 | Preparation of Basinwide H & H TSDN | 2 mo | 7/16/2002 8:00 | 9/09/2002 17:00 | n/a | Halff |
| 74 | Send Basinwide TSDN to MCC | 0 wks | 9/09/2002 17:00 | 9/09/2002 17:00 | 73 | LCRA |
| 75 | Review Basinwide H & H by MCC (TSDN) | 3 mo | 9/10/2002 8:00 | 12/02/2002 17:00 | 74 | FEMA |
| 76 | Review of Basinwide H & H by LCRA(TSDN) | 3 mo | 9/10/2002 8:00 | 12/02/2002 17:00 | 74 | LCRA |
| 77 | MCC comments on draft Basinwide TSDN to Halff | 0 wks | 12/02/2002 17:00 | 12/02/2002 17:00 | 75 | FEMA |
| 78 | LCRA comments on draft Basinwide TSDN to Halff | 0 wks | 12/02/2002 17:00 | 12/02/2002 17:00 | "77,76" | LCRA |
| 79 | Prepare final Basinwide TSDN | 4 wks | 12/03/2002 8:00 | 12/30/2002 17:00 | 78 | Halff |
| 80 | Basinwide TSDN final report | 0 wks | 12/30/2002 17:00 | 12/30/2002 17:00 | 79 | Halff |
| 81 | Prep & Submittal of Individual County (TSDN) | 32 wks | 1/06/2003 8:00 | 8/15/2003 17:00 | n/a | Halff |
| 82 | Wharton County (TSDN) | 16.2 wks | 1/06/2003 8:00 | 4/28/2003 17:00 | n/a | Halff |
| 83 | Preparation of draft TSDN for Wharton | 9.2 wks | 1/06/2003 8:00 | 3/10/2003 17:00 | n/a | Halff |
| 84 | Review of draft TSDN Wharton by MCC | 4 wks | 3/11/2003 8:00 | 4/07/2003 17:00 | 83 | FEMA |
| 85 | Review of draft Wharton TSDN by LCRA and TCRFC | 4 wks | 3/11/2003 8:00 | 4/07/2003 17:00 | 83 | LCRA |
| 86 | MCC comments on Wharton Draft TSDN sent to Halff | 0 wks | 4/07/2003 17:00 | 4/07/2003 17:00 | 84 | FEMA |
| 87 | LCRA/TCRFC comments on Wharton Draft TSDN sent to Halff | 0 wks | 4/07/2003 17:00 | 4/07/2003 17:00 | "86,85" | LCRA |
| 88 | Preparation of Final Wharton TSDN submittal | 3 wks | 4/08/2003 8:00 | 4/28/2003 17:00 | 87 | Halff |
| 89 | Wharton TSDN transmitted to FEMA | 0 wks | 4/28/2003 17:00 | 4/28/2003 17:00 | 88 | LCRA |
| 90 | Bastrop County (TSDN) | 32 wks | 1/06/2003 8:00 | 8/15/2003 17:00 | n/a | Halff |
| 91 | Preparation of draft TSDN for Bastrop | 9.2 wks | 1/06/2003 8:00 | 3/10/2003 17:00 | n/a | Halff |
| 92 | Review of draft TSDN Bastrop by MCC | 4 wks | 3/11/2003 8:00 | 4/07/2003 17:00 | 91 | FEMA |
| 93 | Review of draft Bastrop TSDN by LCRA and TCRFC | 4 wks | 3/11/2003 8:00 | 4/07/2003 17:00 | 91 | LCRA |
| 94 | MCC comments on Bastrop Draft TSDN sent to Halff | 0 wks | 4/07/2003 17:00 | 4/07/2003 17:00 | "92,93" | FEMA |
| 95 | LCRA/TCRFC comments on Bastrop Draft TSDN sent to Halff | 0 wks | 4/07/2003 17:00 | 4/07/2003 17:00 | 93 | LCRA |
| 96 | Preparation of Final Bastrop TSDN submittal | 5 wks | 4/08/2003 8:00 | 5/12/2003 17:00 | "95,94" | Halff |
| 97 | Bastrop TSDN transmitted to FEMA | 0 wks | 8/15/2003 17:00 | 8/15/2003 17:00 | 96 | LCRA |
| 98 | Activity 7: DFIRM Production | 162.6 wks | 6/03/2002 8:00 | 7/13/2005 17:00 | n/a | Halff |
| 99 | Activity 7: DFIRM Production-Wharton | 153.6 wks | 8/05/2002 8:00 | 7/13/2005 17:00 | n/a | Halff |
| 100 | Prep & Submit Camera Ready DFIRM | 153.6 wks | 8/05/2002 8:00 | 7/13/2005 17:00 | n/a | Halff |
| 101 | Collect all (raster & vector) base mapping data for Wharton | 4 wks | 1/27/2003 8:00 | 2/21/2003 17:00 | n/a | Halff |
| 102 | Project/Rectify all base mapping data to coordinate system-Wharton | 5 wks | 2/24/2003 8:00 | 3/28/2003 17:00 | n/a | Halff |
| 103 | Review DFIRM paneling system for Wharton | 4 wks | 8/05/2002 8:00 | 8/30/2002 17:00 | n/a | FEMA |
| 104 | Assemble all hydraulics mapping data for Wharton | 4.2 wks | 4/14/2003 8:00 | 5/12/2003 17:00 | n/a | Halff |
| 105 | Create BFE's for Wharton | 4 wks | 5/13/2003 8:00 | 6/09/2003 17:00 | 104 | Halff |
| 106 | Prepare draft Wharton DFIRM panels & submit for review | 6 wks | 6/10/2003 8:00 | 7/21/2003 17:00 | 105 | Halff |
| 107 | Prepare draft Wharton DFIRM database & submit for review | 6.2 wks | 7/21/2003 8:00 | 9/01/2003 17:00 | n/a | Halff |
| 108 | Review of DFIRM submital by MCC-Wharton | 12.2 wks | 9/08/2003 8:00 | 12/01/2003 17:00 | n/a | FEMA |
| 109 | Review of DFIRM submittal by LCRA-Wharton | 12.2 wks | 9/08/2003 8:00 | 12/01/2003 17:00 | n/a | LCRA |
| 110 | "Prepare & submit ""camera ready"" Wharton DFIRM panels & database in GIS/CADD format" | 5 wks | 12/01/2003 8:00 | 1/02/2004 17:00 | n/a | Halff |
| 111 | TCRFC Review of DFIRM Wharton submittal | 4.2 wks | 1/05/2004 8:00 | 2/02/2004 17:00 | 110 | TCRFC |
| 112 | LCRA transmits Wharton DFIRM to FEMA | 0 wks | 2/02/2004 17:00 | 2/02/2004 17:00 | 111 | LCRA |
| 113 | Preliminary Processing for Wharton | 4.4 mo | 2/03/2004 8:00 | 6/03/2004 17:00 | 112 | FEMA |
| 114 | Community Review(30 days)-Wharton | 4.2 wks | 6/04/2004 8:00 | 7/02/2004 17:00 | 113 | FEMA |
| 115 | Final CCO meeting-Wharton | 0 wks | 7/02/2004 17:00 | 7/02/2004 17:00 | 114 | FEMA |
| 116 | Revisions by MCC & Public Notices(2)-Wharton | 10 wks | 7/05/2004 8:00 | 9/10/2004 17:00 | n/a | FEMA |
| 117 | 90 day Appeal Period-Wharton | 17.4 wks | 9/13/2004 8:00 | 1/11/2005 17:00 | 116 | FEMA |
| 118 | Final Maps by Gov Print Office-Wharton | 26.2 wks | 1/12/2005 8:00 | 7/13/2005 17:00 | 117 | FEMA |
| 119 | Community/County Ord updates with release of Final Printed Maps for Wharton | 26.2 wks | 1/12/2005 8:00 | 7/13/2005 17:00 | n/a | FEMA |
| 120 | Coordinate the map maintenance plan with TNRIS(Submission for Public Viewing) for Wharton | 0 wks | 7/13/2005 17:00 | 7/13/2005 17:00 | 119 | Halff |
| 121 | Activity 7: DFIRM Production - Bastrop | 143.4 wks | 6/03/2002 8:00 | 3/02/2005 8:00 | n/a | Halff |
| 122 | Prep & Submit Camera Ready DFIRM | 143.4 wks | 6/03/2002 8:00 | 3/02/2005 8:00 | n/a | Halff |
| 123 | Collect all (raster & vector) base mapping data for Bastrop | 4 wks | 11/04/2002 8:00 | 11/29/2002 17:00 | n/a | Halff |
| 124 | Project/Rectify all base mapping data to coordinate system for Bastrop | 5 wks | 12/02/2002 8:00 | 1/03/2003 17:00 | 123 | Halff |
| 125 | Review Bastrop DFIRM paneling system for selected counties | 4 wks | 6/03/2002 8:00 | 8/30/2002 17:00 | n/a | FEMA |
| 126 | Assemble all hydraulics mapping data for Bastrop | 2 wks | 2/04/2003 8:00 | 2/17/2003 17:00 | n/a | Halff |
| 127 | Create BFE's-Bastrop | 4 wks | 2/18/2003 8:00 | 3/17/2003 17:00 | 126 | Halff |
| 128 | Prepare Draft Bastrop DFIRM panels & submit for review | 6 wks | 3/18/2003 8:00 | 4/28/2003 17:00 | 127 | Halff |
| 129 | Prepare Draft Bastrop DFIRM database & submit for review | 6 wks | 4/29/2003 8:00 | 6/09/2003 17:00 | 128 | Halff |
| 130 | Review of Submittal by MCC-Bastrop | 13.4 wks | 6/10/2003 8:00 | 9/10/2003 17:00 | n/a | FEMA |
| 131 | Review of DFIRM submittal by LCRA-Bastrop | 25 wks | 6/10/2003 8:00 | 12/01/2003 17:00 | 129 | LCRA |
| 132 | "Prepare & submit ""camera ready"" Bastrop DFIRM panels & database in GIS/CADD format" | 4.6 wks | 9/11/2003 8:00 | 10/13/2003 17:00 | 130 | Halff |
| 133 | TCRFC Review of DFIRM Bastrop submittal | 3.8 wks | 10/14/2003 8:00 | 11/07/2003 17:00 | n/a | TCRFC |
| 134 | LCRA transmits Bastrop DFIRM to FEMA | 0 wks | 11/07/2003 17:00 | 11/07/2003 17:00 | 133 | LCRA |
| 135 | Preliminary Processing for Bastrop Maps | 17 wks | 11/10/2003 8:00 | 3/05/2004 17:00 | 134 | FEMA |
| 136 | Community Review(30 days) for Bastrop Masp | 4.8 wks | 3/08/2004 8:00 | 4/08/2004 17:00 | 135 | FEMA |
| 137 | Final CCO meeting-Bastrop | 0 wks | 4/08/2004 17:00 | 4/08/2004 17:00 | 136 | FEMA |
| 138 | Revisions by MCC & Public Notices(2)-Bastrop | 7.2 wks | 4/12/2004 8:00 | 5/31/2004 17:00 | 137 | FEMA |
| 139 | 90 Day Appeal Period-Bastrop | 13.4 wks | 6/01/2004 8:00 | 9/01/2004 17:00 | 138 | FEMA |
| 140 | Final Maps by Gov Print Office for Bastrop | 26 wks | 9/01/2004 8:00 | 3/01/2005 17:00 | n/a | FEMA |
| 141 | Community/County Ord updates with release of Final Printed Maps for Bastrop | 26 wks | 9/01/2004 8:00 | 3/01/2005 17:00 | n/a | FEMA |
| 142 | Coordinate the map maintenance plan with TNRIS for Bastrop | 0 wks | 3/02/2005 8:00 | 3/02/2005 8:00 | n/a | Halff |
| 143 | Activity 7: Other DFIRM Production -Wharton | 60.6 wks | 8/05/2002 8:00 | 10/01/2003 17:00 | n/a | FEMA |
| 144 | Activity 7: Other DFIRM Production - Bastrop | 73.8 wks | 8/05/2002 8:00 | 1/01/2004 17:00 | n/a | FEMA |
| 145 | Activity 8: Progress Meetings & Rpts | 104.6 wks | 11/30/2001 8:00 | 12/02/2003 17:00 | n/a | FEMA |
| 146 | Wharton CCO Meetings | 0 wks | 6/20/2002 8:00 | 6/20/2002 8:00 | n/a | FEMA |
| 147 | Initial CCO Meeting | 0 wks | 6/20/2002 8:00 | 6/20/2002 8:00 | n/a | FEMA |
| 148 | Bastrop CCO Meetings | 0 wks | 6/20/2002 8:00 | 6/20/2002 8:00 | n/a | FEMA |
| 149 | Initial CCO Meeting | 0 wks | 6/20/2002 8:00 | 6/20/2002 8:00 | n/a | FEMA |
| 150 | FEMA Reports to TCRFC | 104.6 wks | 11/30/2001 8:00 | 12/02/2003 17:00 | n/a | FEMA |